Planned Value Calculator
Compute Planned Value (PV) and full EVM metrics — SV, CV, SPI, CPI, EAC — with traffic-light status indicators.
Project Inputs
$
Total approved project budget.
%
What % should be done by today per the schedule.
Optional — Full EVM Dashboard
%
How much of the project is actually done.
$
Total money spent to date.
Enter BAC and Planned % Complete, then click Calculate.
Planned Value (PV)
Budget for work scheduled to be done by now. PV = BAC × Planned %
Earned Value (EV)
Budget for work actually completed. EV = BAC × Actual %
EVM Performance Metrics
Interpretation
Summary
Compute Planned Value (PV) and full EVM metrics — SV, CV, SPI, CPI, EAC — with traffic-light status indicators.
How it works
- Enter Budget at Completion (BAC) — total approved project budget.
- Enter Planned % Complete — what fraction of the project should be done by today per the schedule.
- PV (Planned Value) = BAC × Planned % Complete is calculated instantly.
- Optionally enter Actual % Complete and Actual Cost (AC) to unlock the full EVM dashboard.
- SV, CV, SPI, CPI, and EAC are computed and displayed with green/yellow/red indicators.
Use cases
- Track whether a project is ahead or behind schedule at any checkpoint.
- Calculate cost efficiency of completed work versus dollars spent.
- Forecast the total cost at project completion using CPI-based EAC.
- Present a concise EVM status summary in stakeholder reports.
- Cross-check outputs from MS Project or Primavera with a quick manual calculation.