CPI & SPI Calculator
Enter Earned Value, Planned Value, and Actual Cost to instantly compute your project's Cost Performance Index (CPI) and Schedule Performance Index (SPI) with status interpretation.
Project Values
Enter dollar amounts (or any consistent unit). Decimals OK.
Formulas
CPI= EV / AC
SPI= EV / PV
CV= EV − AC
SV= EV − PV
Enter EV, PV, and AC then click Calculate
CPI, SPI, and variance values will appear here
Cost Performance Index (CPI)
How efficiently budget is being spent
—
= EV / AC
00.81.01.22.0+
Schedule Performance Index (SPI)
How efficiently scheduled time is being used
—
= EV / PV
00.81.01.22.0+
Cost Variance (CV)
—
EV − AC
Schedule Variance (SV)
—
EV − PV
Summary
Enter Earned Value, Planned Value, and Actual Cost to instantly compute your project's Cost Performance Index (CPI) and Schedule Performance Index (SPI) with status interpretation.
How it works
- Enter the Earned Value (EV) — the budgeted cost of work actually completed to date.
- Enter the Planned Value (PV) — the budgeted cost of work that was scheduled to be done by now.
- Enter the Actual Cost (AC) — the real money spent on the work completed to date.
- Click Calculate to see CPI, SPI, Cost Variance, and Schedule Variance.
- Read the status badges and interpretation text to understand project health.
Use cases
- Quickly check whether a project is over budget (CPI < 1) or under budget (CPI > 1).
- Determine if work is behind schedule (SPI < 1) or ahead of schedule (SPI > 1).
- Prepare a concise status report for a PMO or stakeholder meeting.
- Study for the PMP exam by verifying EVM index calculations.
- Compare CPI and SPI side by side to diagnose whether a project has a cost problem, a schedule problem, or both.
- Track project performance trends across sprint or phase boundaries.
Frequently Asked Questions
Last updated: 2026-07-01 ·
Reviewed by Nham Vu