PERT Estimate Calculator

Enter optimistic, most likely, and pessimistic durations to get a PERT weighted estimate, standard deviation, and confidence range.

Task Inputs

Enter three time estimates per task.

Copied!

Summary

Enter optimistic, most likely, and pessimistic durations to get a PERT weighted estimate, standard deviation, and confidence range.

How it works

  1. Enter the optimistic duration — the best-case time if everything goes perfectly.
  2. Enter the most likely duration — your realistic day-to-day estimate.
  3. Enter the pessimistic duration — the worst-case time if major problems occur.
  4. Select the unit (hours, days, weeks, or months) for all three values.
  5. The PERT expected duration is computed as (O + 4M + P) / 6.
  6. Standard deviation is (P - O) / 6; the confidence range is Expected ± 3 × SD.

Use cases

Frequently Asked Questions

Related tools

Last updated: 2026-05-29 · Reviewed by Nham Vu